The decision was made by the Board of Directors on September 11, 2025, as the contractor failed to perform its duties and meet the deadlines.

The contract between the parties, signed in April 2023, stipulated completion of works and commissioning of CTE Iernut by building a new combined cycle gas turbine power plant, a project considered strategic for Romania’s national energy system.

The notice of termination will take effect on the 31st day from the receipt of the notification by the other party, Romgaz said.

The Iernut plant project started in 2016 and has experienced delays and changes of contractors. Its completion is essential for boosting  the production capacity of electricity from natural gas and for balancing the country’s energy system.