Last week, Romgaz announced it concluded a contract of EUR268.8 billion with Spanish company Duro Felguera and Romelectro for the construction of a new thermal power plant in Iernut, Mures County. The main equipment will be delivered at the beginning of 2018 by Duro Felguera, while Romelectro will be in charge with the construction works, engineering works and the delivery of auxiliary equipment.
The thermal power plant in Iernut will have a total installed capacity of 430 MW. The project will be financed from Romgaz own sources and funds from the National Investment Plan.
Romgaz took over Iernut in February 2013 from Electrocentrale Bucharest, to extinguish a debt of RON653 million.
Romgaz is 70% owned by the Romanian state, through the Ministry of Economy.
Romelectro is contractor, developer and investor in energy projects. The group includes four companies – Romelectro SA and other three firms in which Romelectro is majority shareholder: the Institute for Energy Studies and Design (ISPE), CELPI and Electromontaj Carpati Sibiu.