The ministry had held auctions for nine highway sections. Five contracts were signed in May, three were signed Tuesday and the final contract will be signed soon, after the dispute resolution council (CNSC) solves the final contestation.

The 82 km-long Orastie-Sibiu highway was divided into four sections. The contract for section 3 was signed in May, as its auction was not challenged.

The contract for the first section (24 km) was awarded to Austrian company Strabag, for EUR166.65 million, with VAT. The auction had been contested by the association Tehnologica Radion/Gabriel Couto/Amandio Carvalho/Lena /Rosas/Arcadis.

The second section (20 km) will be designed and built by Romania’s Straco Grup and Italy’s Studio Corona SRL Civil Engineering, for EUR114.26 million, with VAT. The CNSC rejected the challenge filed by Max Boegl Romania/Geiger/Tancrad/Primacons.

The auction for section 4 (around 17 km) was won by the Italian-Romanian consortium Astaldi-Euroconstruct Trading ’98-Astalrom for EUR146.63 million. It had been contested by Romanian company J&P-Avax.

Every contract allows 4 months design time and 18 months for construction, plus 4 years warranty. Financing comes from European Union funds (85%) and the state budget.

Section 3 will be designed and built by Italian firm Impregilo, for EUR182.91 million.

In May, the ministry signed the contracts for the Timisoara-Lugoj (section 1), Nadlac-Arad (both sections) and Lugoj-Deva (section 1) segments. The auction for section 2 of the Timisoara-Lugoj segment was won by Italian consortium Tirrena Scavi-Societa Italiana per Condotte d’Acqua-Cossi Construzioni, with its offer of 445.64 million lei (EUR107 million). It was contested by Confort SA Timisoara-Monteadriano, Tehnologica Radion-Gabriel Couto-Amandio Carvalho-Lena-Rosas-Arcadis and the association Construcciones Y Promociones Balzola-Robert Alcisa-Puentes.

Prime Minister Emil Boc on Tuesday asked the constructors to stick to the projects’ schedules and quality standards. He warned that Romania will not accept work below the standards used in other EU states. (EUR1=RON4.1544)