CNADNR is to terminate its current contract with Italian association Pizzarotti – Tirrena Scavi for the construction of the 3.3 km.

The Bucharest – Ploiesti highway was opened to traffic in the summer of 2012, with speed limits, but the first 6.5 km have not yet been finalized. Construction works on the 6.5-km highway section set off in 2012, of which 3.2 km currently are 98% completed and the first 3.3 km are only 5% completed.

The set of measures for the first 3 km (from km 0+000 to km 3+325) provides informing the entrepreneur of the termination of contract, by February 16, and the new contract awarding procedures are to be completed by the end of June 2015.

Mid-2014, former transport minister Dan Sova said CNADNR had informed the builders of the first 6.5 km of the Bucharest-Ploiesti of the termination of the construction contract.