The contract targets design works, as well as technical assistance and construction works for the modernization of the bypass route between highway A1 and national road DN 7 and between national road DN 2 and highway A2, second lot: section between national road DN2 (km 12+300) and highway A2 (km 23+750).
The contract was awarded through open tender and the funds will be entirely covered from the state budget.
The implementation of the contract consists of 90 days for design works, 450 days for construction works and a grace period of 48 months. (EUR1=RON4.4939)