The two stations will allow the delivery of natural gas to the national transmission system, at pressures of up to 40 bar. Nearly 7.5% of OMV Petrom’s gas production in Romania is processed through the two units, which is necessary for 330,000 households.
The natural gas projects in Burcioaia and Madulari include the construction of pipelines to transport gas from gas fields, the construction of stations for drying, compressing and measuring natural gas, as well as the infrastructure needed for connection to the national gas transmission system. Construction works on the two projects required nearly 1.3 million hours of work.