In mid-March, when winter was not totally departed, there were a few tens of workers both on the construction site of the Promenada mall in northern Bucharest, which is scheduled for opening in 2013, and at the Cora Alexandriei and Kaufland Mihai Bravu projects, which should be completed by the end of this year.

On the plot nearby Titan lake, where the ParkLake Plaza mall is supposed to be built, there was only an excavator of Apolodor company, but it was not working.

Last week, signs of progress were obvious on the first three construction sites, while on ParkLane, a project developed by a group of investors from Ireland, the non-working excavator was gone.

Caelum announced in the autumn of last year it had started works on ParkLake, a EUR250 million investment, but six months later there has been no noticeable progress on the construction site. However, representatives of the investor say the completion deadline remains the same, namely the fourth quarter of 2013.

“We are in negotiations to appoint the general contractor. As soon as he is appointed, we will make an official announcement,” said Caelum representatives.

They explain the lack of activity on the construction site through what was found when the pillars were tested. They found the soil beneath the future mall to be better quality than originally anticipated, so they resorted to “streamlining the building’s foundation works both financially and in terms of the duration of the construction.”

Nearby Rahova bus terminal, where French-held Cora is building its four hypermarket in Bucharest through Albro Estate company, two small-sized cranes had by last week erected around 20 pillars of the future structure, and Holcim mixers were busy going in and out of the construction site. In mid-March, no pillar had been erected – the pillars supplied in one piece and carried in trucks.

The deadline announced for this project – end of this year, appears to be quite ambitious. However, such buildings have a simple architecture, so the hypermarket at least could be delivered within the next seven or eight months. The builder of the project is Con-A company in Sibiu.

Germany’s Kaufland is also working on the company’s fourth hypermarkets in Bucharest. A good part of the structure has already been finalized, and the installing of the rooftop started last week.

Kaufland is building both its own store and a shopping gallery that has already been rented out by developer InterCora to Domo, Deichmann, Takko and KFC.

Workers on the construction site are confident the construction will be finalized by the end of this year, considering that the construction authorization is valid until mid-November.

The most important shopping center construction site that is under way in Bucharest is that of the Promenada project in Floreasca (central – north Bucharest), where progress is significant one month from the previous visit. Whereas in mid-March not even the pit for the foundation was dug, one month later the foundation raft was laid and Strabag workers are working on the first floor of the underground parking lot.

This mall is scheduled for completion by the autumn of next year. However, Austria’s Raiffeisen Evolution, the developer of the project, has already rented out almost 70% of the project’s 36,000 square meter leasable area.

The project’s future tenants include Billa, Zara, H&M, C&A, Flanco and Pure Fitness, which will seek to attract as customers the employees of companies based in the Barbu Vacarescu – Floreasca area, the new hub of the Bucharest office market.

The investment in the project exceeds EUR100 million and Austrian bank Raiffeisen has within the past few months approved a loan to finance construction of this mall.

Prospective projects

The leading mall in Bucharest, where works should have started this year, is Mega Mall in Pantelimon, near National Arena, whose developers announced that construction would start this autumn.

As for Auchan representatives, they said this week would see the start of works on Auchan City Giulesti, a smaller project which should be completed by the end of this year, while the development of other malls could start in Bucurestii Noi (Victoria City and AFI Palace B.NOI) and Colentina (on the Helitube platform).

(English version by Daniela Stoican)