The announcement comes after several months of passenger complaints.
The investment will be carried out over a 30-month period, with works set to unfold in stages. Investment design is set to last at least eight months.
The contract is totally worth RON112 million and CNAB has signed with a three-company association, namely Uti Construction and Facility Management, Somet and Re Act Now Architecture.
(English version by Catalina Apostoiu)