Only 20 kilometers of Bucharest’s beltway have been upgraded in five years of work, despite the spending of more than EUR12 billion by the Transport Ministry. Part of the money went to similar projects worth hundreds of millions of euros in other cities, which are completed or are already in operation.

The Transport Ministry budget amounted to almost EUR6 billion in 2007-2008, according to the data on its website, while the 2008-2012 allocation for infrastructure projects stood at EUR12 billion, according to Ziarul Financiar’s calculations.

Meanwhile, the Bucharest beltway, a 72 kilometer-long road, got only EUR90 million for upgrade works, according to the data provided by the national company in charge of Romania’s highways and national roads (CNADNR). The real upgrade was only done on a 20-kilometer section in the north of the city.

Contacted by ZF, Ludovic Orban, former Transport minister in office when work on the beltway started, says he left contracts signed for the upgrade of the entire road worth EUR100 million when he left his position in 2008. The completion deadline at the time was three years. His successors, Radu Berceanu and Anca Boagiu could not be reached for comment.

Work is progressing extremely slowly and the capital city has received less and less money in the last two years, compared with other major cities, which got more for similar projects. A Business Construct magazine analysis of the data provided by CNADNR shows that three cities in Romania have received more money than Bucharest for beltway works since early 2011. The three cities are Suceava with more than EUR26 million, Iasi with some EUR24 million and Cluj with about EUR23 million (north, NE and NW of Romania).

Bucharest ranked fourth with EUR16.5 million. The authorities have a small step approach when it comes to its beltway and completion is nowhere in sight.

Five years after the start of the rehabilitation work on the capital city’s beltway, a big problem persists, though. Many of the intersections of the beltway with the 18 exit ways from Bucharest are choked with traffic in the absence of any over or underpass to facilitate getting out of the city to towns like Cernica and Domnesti (SE and SW of Bucharest), writes Business Construct. Further compounding the problem, at least in the south part of the city are the seven or eight sets of railroad tracks once going to the yards of storage facilities or plants, which are of no use to anyone today. However, they are still in place and causing significant traffic slowdown, considering a lot of the traffic in the outskirts of Bucharest is generated by heavy-duty trucks.

Another serious issue is the increase in daily vehicle traffic in the city, because motorists have no other option but to drive through it to get to their destination.

(English version by Loredana Fratila-Cristescu)