The facility will have a nominal installed capacity of approximately 20 MW and a storage capacity of approximately 40 MWh.
Works would last around seven months from the date of contract signing.
The battery system is designed to store electricity generated during periods of high renewable production and make it available when demand is higher, contributing to better grid stability and more efficient use of renewable energy.
Construction work is currently underway at the Isalnița photovoltaic park. It will have an installed capacity of approximately 89 MWp and is estimated to generate around 130 GWh of renewable electricity annually.
The operation and maintenance services (“O&M”), to be provided over a period of two years, are not included in the above-mentioned value and will be covered by a separate purchase order.
Simtel says the project is in line with its announced strategy, which focuses on implementing large-scale projects for relevant market clients.
(English version by Catalina Apostoiu)