The board suspended the procedure over irregularities found in the task book released by the national road authority CNADNR, contested by law firm Bostina si Asociatii.

“We contested the award procedure because, on the one hand, the task book contained illegal and discriminatory clauses which would have restricted the access of economic operators to the public auction, gravely affecting, on the other hand, the principles governing public procurement contract award procedures,” lawyer Doru Catalin Bostina said in a press release.

The highway section in question was partly open to traffic in July and the section is expected to be completed by January 2013.