The BESS projects in Vulturul and Fantanele are scheduled for completion in 2026-2027.
Apart from energy storage investments, Electrica is carrying out a EUR253 million investment in the Crucea Est wind farm project, a EUR28 million investment in the Satu Mare 3 photovoltaic (PV) project, and another EUR36 million in the Bihor 1 photovoltaic project. The wind farm is due for completion in 2027-2028 and the two solar power parks in 2027.
The green bond issuance has an interest rate of 4.375% per annum and is due on July 14, 2030.
Electrica Group has a stock market capitalization of RON14 billion. The Group has budgeted a consolidated net profit of RON281 million in 2026, down 73% from RON1.045 billion reported in 2025.