Works on the 14-long Ionesti-Varfurile section have been nearly 30% completed and a new constructor will be selected through auction.

The contract for the rehabilitation of 51 km between Beius and Oradea was also terminated. The roads authority launched acquisition procedures for the rehabilitation of road structure and upkeep works are ongoing.

CNADNR head Narcis Neaga said the roads authority will continue checkups on the construction sites of Deva – Oradea national road in the upcoming period.

DN 76 (184 km long) is the main route connecting the cities of Deva and Oradea in western Romania.