The tender has been divided into eight sections – the Transylvania Highway, between Campia Turzii and Gilau (RON7.35 million), Cluj (RON52.35 million), Bistrita (RON35.11 million), Oradea (RON57.07 million), Baia Mare (RON40.16 million), Alba (47,8 milioane lei), Satu Mare (RON27.89 million) and Zalau (RON31.73 million).
The Cluj and Bistrita sections received bids from the consortium Drum Inserv – Athos – Ritorsa Trans; the Oradea section was bid on by consortia Trans Bitum – Euroconstruct Trading 98 – Drumuri si Poduri Salaj, Ritorsa – Athos Com – Vakond, Simarc – Alpha Design Build Group – Argecom – Valah Construct Grup and Hidroconstructia – Corporate Management Solutions.
The contract for maintenance on roads in the Baia Mare region received bids from XS Sud Compani, Selina and Diferit, and from the consortia Drum Inserv – Athos Com – Ritorsa Trans, Argecom – Alpha Design Build Group – Simarc – Valah Construct Grup; the Alba contract was bid on by Newamport Compani and Selena, and the consortia Alpha Design Build Group – Argecom – Simarc – Valah Construct Grup and Hidroconstructia – Corporate Management Solutions.
The Satu Mare contract attracted the interest of XS Sud Compani and Selina, and of the consortium Athos Com – Ritorsa Trans – Vakond; the Zalau section received bids from Diferit and Drum Construct, and from the consortia Trans Bitum – Euroconstruct Trading 98 – Drumuri si Poduri Salaj and Athos Com – Ritorsa Trans – Vakond.
The frame-contract for the Cluj branch for 2008-2011 was worth RON374 million and delivered by five consortia that included companies such as Spedition UMB, Tehnostrade, Han Grup, Ritorsa Trans, Loial Impex și Euroconstruct Trading ’98, as well as a single company – Diferit SRL.
CNADNR signed multi-year road maintenance contracts for every branch in the country for the 2008-2011 interval worth around EUR1 billion. The contracts were extended at the end of last year until March 31.
Out of its total budget for maintenance in the last four years, CNADNR claims to have paid only EUR254 million to the contractors. (EUR1=RON4.378)