The association won the auction for the contract, which was signed Monday with CNADNR.

The project will be financed from the state budget and is for the design and construction of the road from km 0 to 44+130, and from km 51+041 to 109+905. The design will take two months and construction ten months; the companies must provide ten years as warranty.