According to the latest data from Transelectrica, 43 wind farms have got a network connection contract since the start of the year. This is a major step in carrying out such an investment, with companies able to start construction works after this stage.
The region for which most contracts have been signed in 2011 is Galati, with 18 such contracts. The list of investors that set their eyes on Galati includes companies such as Electrica or Energias de Portugal, companies which are developing or have completed extensive projects in Dobrogea.
The next county on investors’ list this year is Vaslui, where connection contracts for 6 wind farms have been issued, and the list of interested investors includes again Energias de Portugal, but also Germany’s Prowind that collaborates with GE US giant.
“In Dobrogea, network connection contracts have already been signed in the past years, which is prompting investors interested in wind farms to choose other areas with potential. Moldavia is one of them,” says Dana Duica, head of the Romanian Association for Wind Energy.
Botosani and Suceava have also been noticed by investors, who signed five contracts in the two counties. The investors include Germany’s E.ON, which entered Romania in 2005.
The region of Moldavia thus becomes the second important one after Dobrogea as regards wind farm investment plans. Considering that Moldavia is Romania’s poorest region, investors’ interest in wind farms in this area is likely to attract considerable funds in the following years and create new jobs.
“Around 1,500 MW are in various stages of development in the Moldavia area. These projects entail total investments of EUR2.7 billion. (…) The capacity set to be installed in this area generates 2,500 jobs,” adds Duica.
Over the past two years, wind energy projects have attracted investments of above EUR1 billion and created around 1,000 jobs.
(English version by Catalina Apostoiu; Editing by Radu Bostan)