It also meant a new bridge over the Danube, connecting Calafat in Romania to Vidin in Bulgaria, and more than 100 kilometers of new highways (most of which to be opened by yearend).
1. Termination of Bechtel contract
Romania’s national company in charge of national roads and highways, CNADNR, terminated the last contract it had with the US’ Bechtel, which was supposed to build the more than 400 kilometer-long Transylvania Highway. The US company collected more than EUR1.4 billion for merely 52 kilometers of highway completed and another 64 kilometers only half completed between Suplacu de Barcau – Bors (west of the country). After the termination this year the Bechtel was supposed to get another EUR37 million as compensation, according to the agreement with the Romanian government. The Bechtel contract was signed during the Adrian Nastase Government in 2003.
2. CFR Marfa privatization failure
Regarded as one of the most important events of this year, the privatization of CFR Marfa, the country’s largest freight rail carrier was not completed in the end. The privatization failed after the company announced as the winner of the tender organized by the government, Grupul Feroviar Roman (GFR) of businessman Gruia Stoica, did not pay EUR170 million, the amount due for the 51% in the company.
3. Resumption of infrastructure payments under SOP-T
The European Commission decided in June to resume payments to Romania via the Sectoral Operational Program – Transport (SOP-T), which means the government was again allowed to send to Brussels requests for reimbursement of the highway and railway works.
The unfreezing of the payments from Brussels was a very significant event as Romania had only gotten EUR11 million from the EU via the SOP-T in May 2012-May 2013, or 0.2% of the total 2007-2013 allocation of EUR4.5 billion. The European Commission sent a notification about payments being halted in July last year and another one in December 2012 announcing payments had been pre-suspended.
4. Railway upgrade – the year’s biggest infrastructure contract
The consortium consisting of Swietelsky (Austria), Strabag (Austria), Alstom (France), Arcada (controlled by Spiru Mantu and Mihai Huma), Euro Construct Trading 98 (Dan Besciu, Sorin Vulpescu) and Transferoviar Grup (Calin Mitica) will repair and upgrade the Vintu de Jos-Simeria railway line for 1.35 billion lei (EUR302 million euros).
Once the railway repaired and upgraded, passenger trains will be able to travel at speeds of up to 160 km/h and freight trains will be able to travel at up to 120 km/h on the about 42-kilometer long section. The deadline for completion is thirty months and the project is 85% EU funded, with the government contributing the rest. This is the biggest infrastructure contract signed this year.
Several highway construction contracts have been signed in 2013, as well, none of which above EUR150 million, though.
5. Change of highway priorities
The government plans to have a highway completed by 2018 that will cross Romania from west to east, connecting Nadlac and Constanta. This highway, however, will no longer pass through Sibiu and Pitesti, as initially set, but take the Sibiu-Brasov-Ploiesti route.
It also promised completion of several other highways by that year, such as Calafat-Craiova-Pitesti, Pitesti-Ramnicu Valcea, Alexandria-Bucharest, Ploiesti-Galati, Brasov-Iasi-Ungheni, Piatra Neamt-Roman, Bors-Oradea-Cluj Napoca-Sebes, Turda-Targu Mures.
Suplacu de Barcau-Gilau, Comarnic-Brasov, Comarnic-Ploiesti and Pitesti-Craiova highway sections should be built, as well, this time via concession contracts.
6. Bucharest’s subway line 5 gets European funds, TBMs start digging
Early this year the completion of the project to build the subway Line 5 in the western Bucharest district of Drumul Taberei that connects it to the city was uncertain because of the lack of funding but the European Commission later included the investment in its SOP-T.
As a result, the subway line got RON400 million funding for this year. The first of the two giant tunnel boring machines started digging the first tunnel of the new line at the end of September. Although the two TBMs arrived in Bucharest in 2012, they only started digging this fall.
7. Inauguration of the Calafat-Viding bridge over Danube
After more than fifty years since the inauguration of the first bridge over Danube connecting Romania and Bulgaria between Giurgiu and Ruse, the second rail and road bridge between the two countries opened this year.
The new bridge built by the two countries together cost almost EUR300 million and is the most important infrastructure project inaugurated in 2013. Romania and Bulgaria signed the agreement to build it in March 2000, but started work on it late because of insufficient funding. This bridge is part of the European corridor connecting Dresden, Germany to Istanbul, Turkey.
8. More than 100 kilometers of new highways
Romania should end 2013 with more than 660 kilometers of highway, as 98 kilometers in the west of the country are scheduled for inauguration in the last few days of this year. After CNADNR opened for traffic 18 kilometers of highway between Simeria and Orastie in May, the 98 expected for inauguration by the end of the month include the first segment of the Lugoj-Deva highway, and segments 1, 2 and 4 of the Orastie-Sibiu highway.
9. Inauguration of new runway of Cluj-Napoca Airport
The first runway built after the fall of the Communist regime in Romania was inaugurated at the Avram Iancu Airport in Cluj-Napoca this fall. Work on the 3,500-meter runway began in September 2011 and the first phase of the runway is 2,100 meters long and cost EUR30 million to EUR40 million paid by the County Council.
10. Government starts concession of three highways
The government started the necessary procedure for the concession of Comarnic-Brasov (58 kilometers), Craiova-Pitesti (121 kilometers) highways and the Bucharest southern beltway (48 kilometers), which will cost some EUR5 billion together.
The government expects work on the three highways it plans to grant concession of to begin next year but has not yet selected the private investors to do it. Contenders include construction companies from Western Europe, Romania, Turkey and China.
The latest attempts of the government to grant concession of the Comarnic-Brasov highway failed, after builders were found in 2010 but suddenly backed out. The government also attempted to have it built in 2004, but deals with the companies assigned to do it fell through, as well. (EUR1=RON4.4643)